East China’s Jiangsu province has revved up the construction of major investment projects and ensured their smooth progress through every possible effort so as to ensure a flying start in the new year. Our report has the story.
Construction on the China Grand Canal Museum is virtually finished with interior decoration and outdoor landscaping in progress.
Song Jianhui, Director of Engineering Construction Department, Yangzhou Sanwan Investment and Development Co., Ltd.
More than 400 workers are working overtime
to promote the construction of the museum
and the landscape greening project
is scheduled for completion
by the end of this month
or the beginning of next month
Constructors are also speeding up the phase I project of the Grand Canal Intangible Cultural Heritage Cultural Park that lies to the east of the museum.
The project will be completed before the end of June to ensure concurrent opening with the Grand Canal Museum of China.
The Journey to the West Amusement Park in Huai’an has eight core projects. The Huaguoshan project includes four major landmark attractions such as the Monkey King roller coaster and the flying theater.
Ma Jieyuan, deputy project manager, Journey to the West Amusement Park
90% of Huaguoshan has completed
the overall effect color
artificial plants and lighting
have been completed
90% of the horse track has been demolished
As a theme park with Chinese characteristics, the Journey to the West Amusement Park will open to visitors in the first half of this year and is expected to receive 2 million tourists each year.