With the last piece of box girder falling on Pier 206 and Pier 207 of the North Approach Bridge of the Shanghai-Suzhou-Nantong Yangtze River Bridge, the construction of the Jiangbei girder in the Nantong-Zhangjiagang section of the Yancheng-Nantong High-speed Railway was completed, signaling the opening of the Nantong section of the railway.

The Nantong-Zhangjiagang section of the Yancheng-Nantong Railway is also part of the Nantong-Suzhou-Jiaxing-Ningbo Railway that will start construction this year.

The last beam erected in Jiangbei this time is located at the corner of the Shanghai-Suzhou-Nantong Railway and the Wuxi-Nantong Expressway.

The bridge erector is only 6.5 meters away from the railway catenary, making it necessary to carry out the task in early morning hours when the railway is not in service.

The 24.3-kilometer-long Nantong-Zhangjiagang section of the Yancheng-Nantong Railway is connected to the southern Yangtze River Railway, which will effectively shorten the distance between northern Jiangsu and the Yangtze River Delta region and promote economic development along the line.