East China’s Jiangsu province has revved up the construction of major investment projects and ensured their smooth progress through every possible effort so as to ensure the fulfillment of this year’s goals for social and economic development. 

The Putaoling Tunnel on the Yixing-Changxing Express was connected on Tuesday, signaling the first time that an expressway was joined up through a tunnel between Jiangsu and Zhejiang.

The 2.5-km-long two-hole separated tunnel was dug from both ends at the same time, shortening the construction period.

The total length of the Jiangsu section of the Yixing-Changxing Expressway is about 25.5 kilometers. When completed in the first half of next year, the expressway will open up the hilly and mountainous barriers between southern Jiangsu and northwest Zhejiang, and build the second fast track between Nanjing and Hangzhou.

In the face of rising water levels, the builders of the Taihu Tunnel on the Suzhou-Wuxi-Changzhou Expressway raised the cofferdam body from 3.6 meters to 4.85 meters.

Concrete pouring of the shaft wall and the water connection operation has been completed on the steel caisson for the foundation of the main tower of the Changzhou-Taizhou Yangtze River Bridge.

The pile foundation construction of the north and south towers of Longtan Yangtze River Bridge went underway as the steel caisson assembly and ground connecting wall construction were launched for the north and south anchors.

Construction of the Jiangyin-Jingjiang Yangtze River Tunnel project started.

The main line of the Wufeng Mountain Yangtze River Bridge wiring project is basically connected and the first heat conduction cable was buried for the intelligent ice and snow removal system.

In the first half of the year, 9.3 billion yuan were injected into he 13 expressway projects under construction undertaken by the Provincial Transportation Engineering Construction Bureau, accounting for 51% of the annual investment.